A cumulative sum control chart, or CUSUM chart, is designed to detect sustained shifts in the level of a process by accumulating evidence across successive observations. An individual measurement may be close enough to the reference that it does not attract attention. A series of measurements leaning in the same direction may tell a different story. The CUSUM method makes that accumulated evidence visible and provides a defined rule for investigating a possible change. This guide develops original numerical examples from fictional production and service operations, explains the difference between an ordinary cumulative total and a tabular monitoring procedure, and shows how to handle reference values, thresholds, subgroup size and responses without confusing a statistical signal with a product acceptance decision.
Quick Answer
Accumulate deviations using upper and lower resetting statistics, compare them with a justified decision interval, and investigate signals without confusing them with individual acceptance decisions.
Table Of Contents
- What A CUSUM Chart Detects
- Worked Example: Calculate An Ordinary Cumulative Sum
- Define The Upper And Lower Tabular Statistics
- Worked Example: Detect A Sustained Upward Change
- Worked Example: Detect A Downward Change
- Select Parameters With A Defined Monitoring Objective
- Account For Subgroups And Time Order
- Implement The Arithmetic In A Spreadsheet
- Investigate A Signal Without Confusing It With Acceptance
- Reusable CUSUM Chart Worksheet
- Frequently Asked Questions
What A CUSUM Chart Detects
The NIST/SEMATECH handbook section on CUSUM control charts explains their usefulness in detecting relatively small shifts in a process mean. A chart accumulates deviations from an established reference level. If the observations repeatedly exceed that level, the accumulated evidence may increase even when no single observation is exceptionally large.
A conventional Shewhart chart and a CUSUM chart answer related monitoring questions, but they use information differently. A simple Shewhart point rule compares the current statistic with control limits. A CUSUM statistic incorporates previous observations in a structured way. The Minitab CUSUM methods and formulas reference distinguishes tabular and V-mask approaches and describes the role of the reference and decision parameters.
The sequence matters. Rearranging the same set of measurements changes the CUSUM history, even if the mean and standard deviation of the observations remain identical. A sustained period of moderately high values can provide a different monitoring signal from a mixture of high and low values distributed throughout the period. Our histogram examples explain how a distribution can summarize the observations without preserving their order. CUSUM complements that perspective by retaining chronological information.
The reference level should represent an appropriately established in-control process or another explicitly justified monitoring reference. It is not automatically the desired customer specification or the average of all observations, including those the team is trying to investigate. An unsuitable reference can cause systematic accumulation even when the underlying arrangement has not recently changed.
Worked Example: Calculate An Ordinary Cumulative Sum
A fictional paper sample preparation operation observes a noncritical dimension with a monitoring reference of 10 units. The first eight measurements are 10.0, 10.3, 9.7, 10.6, 10.7, 10.8, 10.9 and 11.0. All figures in this example are invented. The basic cumulative sum begins at zero and adds the difference between each current observation and the reference.
| Observation | Value | Deviation From 10 | Cumulative Deviation |
|---|---|---|---|
| 1 | 10.0 | 0.0 | 0.0 |
| 2 | 10.3 | 0.3 | 0.3 |
| 3 | 9.7 | −0.3 | 0.0 |
| 4 | 10.6 | 0.6 | 0.6 |
| 5 | 10.7 | 0.7 | 1.3 |
| 6 | 10.8 | 0.8 | 2.1 |
| 7 | 10.9 | 0.9 | 3.0 |
| 8 | 11.0 | 1.0 | 4.0 |
The ordinary cumulative deviation increases after observation three because each later value exceeds the reference. This demonstrates the accumulation mechanism. A negative observation can offset previous positive deviations, and early values can influence the current cumulative total.
A rising total is useful descriptive information, but this calculation alone does not supply a suitable fixed decision limit. An ordinary cumulative sum is not the same statistic as the resetting one-sided tabular CUSUM described below. Applying a limit intended for the tabular procedure directly to these cumulative deviations would change the monitoring rule.
Our behavior over time graph examples explain why a sequence can reveal changes that an overall summary hides. Here the cumulative total is an additional transformed view of the sequence, not a replacement for the original measurements. Retain both so an investigator can determine which observations contributed to a signal.
Define The Upper And Lower Tabular Statistics
The tabular CUSUM uses separate statistics for upward and downward departures. For this example, use the NIST convention in which both statistics are nonnegative. The upper statistic at the current observation equals the greater of zero or the previous upper statistic plus the current observation minus the reference and minus the allowance K. The lower statistic equals the greater of zero or the previous lower statistic plus the reference minus the current observation and minus K.
Both start at zero. In symbols expressed in plain text, Upper(i) = MAX(0, Upper(i−1) + X(i) − Reference − K). Lower(i) = MAX(0, Lower(i−1) + Reference − K − X(i)). A signal occurs when either exceeds the selected decision interval H under the rule used here.
K is a reference value or allowance controlling which deviations tend to accumulate. H is a decision threshold for the accumulated statistic. For a valid statistical monitoring application, these parameters need to be selected in compatible units using the relevant variability, intended shift sensitivity and false-alarm performance. The example deliberately chooses K = 0.25 units and H = 2 units to make the arithmetic clear. They are not statistically validated limits for an actual process.
The lower statistic is sometimes displayed as a negative value in software. The nonnegative convention used here accumulates downward evidence as a positive magnitude. Both display conventions can describe downward monitoring, but a reader must not mix a negative plotting convention with a positive-threshold formula without adjusting the interpretation.
Worked Example: Detect A Sustained Upward Change
Use the eight observations from the ordinary cumulative-sum example. Apply the tabular formulas with reference 10, K = 0.25 and H = 2. The upper statistic starts at zero and the lower statistic starts at zero.
| Observation | Value | Upper CUSUM | Lower CUSUM | Signal Under Strict Exceeds Rule |
|---|---|---|---|---|
| 1 | 10.0 | 0.00 | 0.00 | None |
| 2 | 10.3 | 0.05 | 0.00 | None |
| 3 | 9.7 | 0.00 | 0.05 | None |
| 4 | 10.6 | 0.35 | 0.00 | None |
| 5 | 10.7 | 0.80 | 0.00 | None |
| 6 | 10.8 | 1.35 | 0.00 | None |
| 7 | 10.9 | 2.00 | 0.00 | None |
| 8 | 11.0 | 2.75 | 0.00 | Upper |
At observation two, the upper increment is 10.3 minus 10 minus 0.25, or 0.05. At observation three, the next increment is negative 0.55, taking the provisional upper total below zero. The MAX function resets it to zero. The lower statistic becomes 0.05 because the observation is 0.3 below the reference and the allowance is 0.25.
From observation four onward, successive positive upper increments of 0.35, 0.45, 0.55, 0.65 and 0.75 accumulate. The upper total is exactly 2.00 at observation seven and reaches 2.75 at observation eight. Under the expressly stated rule that a signal requires strictly exceeding H, the first signal occurs at observation eight. A procedure using greater than or equal to H would signal at observation seven. The rule must be documented, and the comparison must use suitable numerical precision rather than rounded display values.
The signal indicates that the monitoring rule has detected accumulated evidence of a possible upward change. It does not prove which event caused the change or that the eighth individual item is unacceptable. Investigate the measurement arrangement and process conditions across the relevant period. Our measurement system analysis examples explain why a change in measurement behavior can create an apparent process shift.
Worked Example: Detect A Downward Change
A separate fictional service observes a defined numerical performance characteristic with the same teaching reference and parameters. Its sequence is 10.1, 9.6, 9.4, 9.3, 9.2 and 9.1. Initialize both statistics at zero because this is a separate example rather than a continuation of the previous sequence.
| Observation | Value | Upper CUSUM | Lower CUSUM |
|---|---|---|---|
| 1 | 10.1 | 0.00 | 0.00 |
| 2 | 9.6 | 0.00 | 0.15 |
| 3 | 9.4 | 0.00 | 0.50 |
| 4 | 9.3 | 0.00 | 0.95 |
| 5 | 9.2 | 0.00 | 1.50 |
| 6 | 9.1 | 0.00 | 2.15 |
The lower statistic accumulates successive increments of 0.15, 0.35, 0.45, 0.55 and 0.65. It exceeds two at observation six. The upper statistic remains at zero throughout. The direction of the detected change is downward, but its practical meaning depends on the characteristic. A decreasing response time may be desirable if accuracy remains intact. A decreasing measured quantity that must meet a minimum requirement may be undesirable.
Do not interpret the direction alone as a verdict about the quality of the process. A monitoring scheme detects changes relative to its reference. The operational decision depends on the underlying requirement, actual consequence and evidence about the change. Our operational definition examples show why the meaning of the observed characteristic must be established before interpreting a number.
Select Parameters With A Defined Monitoring Objective
The NIST discussion of CUSUM average run length explains an important criterion used to evaluate monitoring designs. Average run length concerns the expected number of observations until a signal under specified process conditions. A useful design balances how often it signals while the process is in control against how quickly it detects a shift of practical interest.
Reducing the threshold H generally makes it easier for an accumulated statistic to reach the decision boundary, but it may increase false alarms. Changing K also alters the response to different deviation sizes. The simple examples above were selected for transparent calculation and do not establish either the in-control or shifted-process run-length properties.
A process with individual observations measured in grams and a process with subgroup means measured in grams may require different numerical parameter values. If observations are standardized, the parameters can be expressed in units of the standard deviation of the monitored statistic. If they are expressed in original units, use compatible scale conversions. A value of 0.5 standard deviations is not necessarily 0.5 grams.
For example, if the appropriate reference standard deviation for the monitored statistic is 0.2 units, a standardized allowance of 0.5 corresponds to an original-unit allowance of 0.1 units. A standardized threshold of 5 corresponds to one original unit. This is a unit conversion illustration, not a recommendation that those parameters are suitable for every operation.
Our coefficient of variation examples distinguish absolute and relative dispersion. The relevant spread for a CUSUM design depends on what statistic is actually being monitored. Do not use a relative dispersion percentage as an original-unit standard deviation.
Account For Subgroups And Time Order
Suppose a production study records subgroups of four individual measurements under comparable conditions and monitors each subgroup’s mean. If the individual measurements are independent and have a common standard deviation of 0.8 units, the standard deviation of a subgroup mean of four is 0.8 divided by the square root of four, or 0.4 units.
That calculation depends on the assumptions. If observations within a subgroup are correlated or reflect different products, the usual independent-observation formula may not be suitable. A changing subgroup size can also affect the precision of the monitored means. A chart designed for constant sample size should not silently treat a mean based on one observation as equally precise as a mean based on sixteen observations.
Investigate the data structure before deciding how to standardize the observations. Our data stratification examples explain how a mixture of distinct groups can create an apparent change in an aggregate even when each group remains unchanged. For example, a shift in product mix could move the average of a combined dimension measure without indicating a within-product shift.
Time order should correspond to the actual monitoring sequence. If a delayed data export records an older measurement after newer measurements, sorting by upload time may produce a false picture of the process. Use the appropriate observation timestamp and document how equal timestamps or missing observations are handled.
Implement The Arithmetic In A Spreadsheet
Place the observation number in column A, the measured value in column B, the upper statistic in column C and the lower statistic in column D. Store the reference, allowance and threshold in three separate cells, for example F2, F3 and F4. Enter zero in the initial upper and lower cells in row two, then begin observations on row three.
| Spreadsheet Cell | Illustrative Formula |
|---|---|
| C3 | =MAX(0,C2+B3-$F$2-$F$3) |
| D3 | =MAX(0,D2+$F$2-$F$3-B3) |
| E3 | =IF(OR(C3>$F$4,D3>$F$4),”Investigate”,””) |
Copy the formulas through the appropriate observation rows. Preserve full calculation precision and display rounded values separately. Before using the spreadsheet for actual monitoring, test its handling of blank measurements and errors. A blank cell may be interpreted as zero by a formula, creating an artificial signal. Prevent calculation for an invalid row according to the declared policy rather than silently replace missing observations with numerical values.
Plot the two accumulated statistics and the decision threshold using the same original-unit scale. Where a signed lower-statistic display is used, apply the corresponding negative plotting convention consistently. Keep the original measurements available for diagnosis.
Investigate A Signal Without Confusing It With Acceptance
A statistical signal and an individual specification decision serve different purposes. Imagine an illustrative accepted interval of 8 to 12 units for a noncritical characteristic. All eight values in the upward example lie inside that interval, yet the chosen CUSUM procedure signals. That is not a contradiction: the monitoring procedure responds to accumulated departure from its reference, while the acceptance rule concerns the individual observed value.
A signal can encourage an investigation before more consequential departures appear. It should not automatically authorize arbitrary adjustments to the process. Identify what changed, whether the measurement system is reliable and whether the current reference remains appropriate. Our quality control plan examples explain the relationship between a characteristic, its observation method and the response to an abnormal condition.
If an investigation establishes that a legitimate process redesign has changed the intended operating level, a new baseline and monitoring design may be appropriate. Preserve the previous chart and record the reason and effective date for the change. Do not simply reset the chart after every inconvenient signal to erase evidence of an unresolved condition.
Reusable CUSUM Chart Worksheet
| Field | Record |
|---|---|
| Characteristic | Operational Definition And Units |
| Reference | Established In-Control Level And Evidence |
| Statistic | Individual Value Or Defined Subgroup Statistic |
| Parameters | K, H, Units And Statistical Design Basis |
| Initialization | Starting Values And Reset Policy |
| Sequence | Observation Order, Missing Data And Validity Rules |
| Signal | Exact Comparison Rule And Direction |
| Response | Investigation, Actual Cause Evidence And Verification |
A CUSUM chart provides an interpretable record of accumulated evidence when the data, reference and monitoring design are suitable. The worked examples establish the arithmetic, but practical implementation requires a defensible baseline, parameter selection and response arrangement. Use the chart to investigate changes in the actual process while preserving separate evidence about individual acceptance, operational consequences and the effectiveness of any corrective action.
Frequently Asked Questions
What is a CUSUM chart?
A monitoring chart that accumulates evidence of departure from a reference process level.
Why use CUSUM for small shifts?
It uses information from successive observations rather than examining each measurement in isolation.
What does K represent?
A reference allowance expressed in units compatible with the monitoring statistic.
What does H represent?
The decision interval for the accumulated statistic.
What is the upper CUSUM?
A resetting statistic that accumulates evidence of upward departure.
What is the lower CUSUM?
A statistic designed to detect downward departure under the declared plotting convention.
Is a simple running sum the same as tabular CUSUM?
The tabular method uses reference allowances, resetting rules and a defined decision interval.
Does a signal prove a product is defective?
Statistical monitoring and individual specification decisions are separate.
How are parameters chosen?
Use suitable process variability, desired shift detection and run-length performance.
What should happen after a signal?
Investigate the measurement and process conditions using the appropriate response procedure.