Earned value management, or EVM, brings planned work, demonstrated progress and actual expenditure together in one project performance assessment. Spending less than planned is not necessarily good news if substantially less work has been accomplished. Equally, spending more than planned does not automatically establish poor performance if the project has completed considerably more work than expected. Earned value provides a common budget-based representation for examining these differences. The original fictional examples below show how to calculate performance measures, compare completion forecasts and interpret the results without confusing monetary schedule measures with calendar delays.
Quick Answer
Compare planned value, earned value and actual cost at the same status date. Calculate cost variance as EV minus AC, schedule variance as EV minus PV, CPI as EV divided by AC and SPI as EV divided by PV.
Table Of Contents
- Define The Baseline And Status Date
- Worked Example: A Historical Map Digitization Project
- Calculate Cost Variance And Cost Performance Index
- Calculate Schedule Variance And Schedule Performance Index
- Worked Example: Develop A Work Package Reconciliation
- Select A Credible Earned Value Measurement Rule
- Estimate At Completion Under Several Assumptions
- Calculate Variance At Completion And Required Future Efficiency
- Distinguish A Baseline Change From A Performance Correction
- Reusable Earned Value Worksheet
- Frequently Asked Questions
Define The Baseline And Status Date
The United States Government Accountability Office Cost Estimating and Assessment Guide explains the use of earned value information to integrate cost, schedule and technical accomplishment. A credible assessment depends on a performance measurement baseline that connects the authorized scope to its planned timing and budget.
Planned value, abbreviated PV, is the budgeted value of work scheduled to be accomplished by the status date. Earned value, abbreviated EV, is the budgeted value of work actually accomplished by that date under the applicable measurement rules. Actual cost, abbreviated AC, is the cost incurred for that work under the relevant accounting conventions.
The budget at completion, or BAC, represents the budget associated with the defined scope in the baseline. It is not necessarily the same as every dollar an organization has authorized or reserved for the wider undertaking. The example below assumes that the entire stated project budget is the relevant BAC and that no separate reserve needs to be reconciled.
Our work breakdown structure examples explain how a project’s scope can be organized into meaningful work packages. In EVM, the baseline needs a corresponding budget and an objective way to recognize each package’s accomplishment. Do not assign earned value merely because money has been spent.
Worked Example: A Historical Map Digitization Project
A fictional regional historical society is digitizing a selected collection of non-sensitive historical maps. The authorized project covers inventory preparation, image capture, indexing and a defined final quality review. Its BAC is $20,000. At the reporting checkpoint, the baseline specifies $10,000 of scheduled work. The demonstrated accomplishment is worth $8,000 in baseline budget terms, while recorded actual cost is $9,000.
| Measure | Amount |
|---|---|
| Budget At Completion | $20,000 |
| Planned Value | $10,000 |
| Earned Value | $8,000 |
| Actual Cost | $9,000 |
Actual cost is $1,000 lower than planned value. This is only a comparison against the budgeted value of scheduled work, not necessarily against a separate cash-flow forecast. Yet it has also accomplished $2,000 less budgeted work than planned. The apparent underspending is not sufficient evidence that the project is performing well.
The earned value of $8,000 represents 40% of BAC. The planned value represents 50% of BAC. Neither percentage necessarily represents the fraction of calendar time used. The work may have a budget profile that places more costly activities in particular periods.
Our milestone planning examples distinguish a meaningful achievement from a scheduled date. An earned value measurement should be connected to demonstrable work, not simply the percentage of the reporting period that has elapsed.
Calculate Cost Variance And Cost Performance Index
Cost variance is EV minus AC. In the example, $8,000 minus $9,000 equals negative $1,000. The project has incurred $1,000 more actual cost than the baseline budget value of the work accomplished. This differs from the comparison of actual spending with PV.
The cost performance index is EV divided by AC. Dividing 8,000 by 9,000 gives approximately 0.889. Under this measurement, each dollar of recorded actual cost corresponds to about 89 cents of accomplished baseline budget value.
| Indicator | Calculation | Result |
|---|---|---|
| Cost Variance | 8,000 − 9,000 | −$1,000 |
| Cost Performance Index | 8,000 / 9,000 | 0.889 |
A CPI below one indicates unfavorable cost performance in this defined comparison. A CPI above one indicates that the accomplished baseline value exceeds the associated actual cost. A CPI exactly equal to one indicates equality under the measure.
The figures do not identify why cost performance differs from the baseline. The digitization team might have encountered more difficult maps, required additional review or used a different resource arrangement. Cost records may also be incomplete at the reporting checkpoint. Investigate the actual conditions and accounting cutoff before attributing the variance to a particular cause.
Calculate Schedule Variance And Schedule Performance Index
Schedule variance is EV minus PV. For the historical society, this is $8,000 minus $10,000, giving negative $2,000. The schedule performance index is EV divided by PV, or 0.8.
| Indicator | Calculation | Result |
|---|---|---|
| Schedule Variance | 8,000 − 10,000 | −$2,000 |
| Schedule Performance Index | 8,000 / 10,000 | 0.800 |
Both measures suggest that less budgeted work has been accomplished than scheduled at this checkpoint. However, a schedule variance of negative $2,000 is expressed in budget units, not days. It cannot be translated into a calendar delay without appropriate additional schedule information.
Similarly, SPI of 0.8 does not prove that the project will finish 20% late. The remaining work may follow different paths, depend on particular resources or contain opportunities for recovery. Our Gantt chart examples explain how actual dependencies and work timing affect the modeled completion date.
At final completion, EV and PV may both equal BAC even when the project finishes later than originally planned. Consequently, ordinary budget-based SPI can return to one at completion despite a historical calendar delay. Preserve schedule forecast and milestone evidence alongside the index.
Worked Example: Develop A Work Package Reconciliation
The historical society records the following budget-based observations for four packages. The values reconcile with the original project figures. Each package has a declared progress measurement rule suited to its work.
| Package | BAC | PV | EV | AC |
|---|---|---|---|---|
| Inventory Preparation | 4,000 | 4,000 | 4,000 | 4,200 |
| Image Capture | 8,000 | 4,000 | 3,000 | 3,500 |
| Indexing | 5,000 | 2,000 | 1,000 | 1,300 |
| Final Review | 3,000 | 0 | 0 | 0 |
| Total | 20,000 | 10,000 | 8,000 | 9,000 |
Inventory preparation is complete under its stated rule but has an unfavorable cost variance of $200. Image capture has a cost variance of negative $500 and schedule variance of negative $1,000. Indexing has a cost variance of negative $300 and schedule variance of negative $1,000.
The total variance identifies the project-level condition, while the individual records help locate where investigation may be useful. Do not compute an unweighted average of package CPI values and expect it to reproduce the project CPI. The correct aggregate is total EV divided by total AC for compatible observations.
Our data stratification examples demonstrate why denominator differences matter when combining ratios. A small package and a large package do not necessarily contribute equally to the project-wide measure.
Select A Credible Earned Value Measurement Rule
Suppose the inventory preparation package has four distinct, equally budgeted deliverables of $1,000 each. The approved rule earns that value when each deliverable meets its defined completion condition. If three deliverables are accepted, the package earns $3,000 regardless of how much effort the fourth has consumed.
A different package may legitimately use weighted milestones. For example, its $4,000 budget may be divided between an accepted preliminary record worth $1,000, a verified complete record worth $2,000 and an accepted handover worth $1,000. If only the preliminary record has met its condition, EV is $1,000, not an arbitrary percentage estimated from elapsed time.
These measurement rules are examples rather than a prescription for every type of project work. Some work has a continuing support character and may require a different approved measurement approach. Avoid using a convenient rule that obscures whether discrete deliverables actually exist.
Our acceptance criteria examples explain why the evidence for a completed result should be defined before the work is judged. A consistent earning rule protects the usefulness of EV, particularly when reporting pressure creates incentives to describe unfinished work as complete.
Estimate At Completion Under Several Assumptions
Estimate at completion, or EAC, is a forecast of the total cost at completion. Estimate to complete, or ETC, is the forecast cost of the remaining work. Their relationship is EAC equals AC plus ETC.
In the fictional map project, BAC minus EV equals $12,000. This is the remaining budgeted value of work, not necessarily the forecast actual cost of doing it. If the organization expects the remaining work to be completed exactly at its original budgeted cost, EAC is $9,000 plus $12,000, or $21,000.
If cumulative cost efficiency is assumed to continue for the remainder, an alternative formula is BAC divided by CPI. Using the exact ratio of 8,000 to 9,000 gives EAC of $22,500. The corresponding ETC is $13,500.
Another illustrative forecasting convention applies both current cost and schedule performance indices to the remaining budgeted work. The formula is AC plus (BAC minus EV) divided by CPI times SPI, where the denominator is their product. Here that gives $9,000 plus $12,000 divided by approximately 0.7111, or $25,875.
| Forecast Assumption | EAC | ETC |
|---|---|---|
| Remaining Work At Baseline Budget | $21,000 | $12,000 |
| Cumulative CPI Continues | $22,500 | $13,500 |
| CPI And SPI Affect Remaining Work | $25,875 | $16,875 |
These forecasts are conditional models. They should not be interpreted as a confidence interval or as a set of guaranteed cost outcomes. Applying the SPI factor is appropriate only when the team has a defensible reason to believe that schedule performance affects the remaining cost in the way represented by the formula.
A bottom-up estimate may be more useful when the remaining work is materially different from the work already performed. Review actual resource estimates and any authorized scope changes. Our PERT estimation examples show why a planning estimate should preserve the conditions and uncertainty behind it.
Calculate Variance At Completion And Required Future Efficiency
Variance at completion, or VAC, is BAC minus EAC. Under the CPI-continuation forecast, the result is $20,000 minus $22,500, or negative $2,500.
To-complete performance index, or TCPI, expresses the cost efficiency required for the remaining work to meet a chosen total cost target. If the target is the original BAC, the formula is (BAC minus EV) divided by (BAC minus AC). In this case, $12,000 divided by $11,000 equals approximately 1.091.
Achieving the original $20,000 total would therefore require about $1.09 of budgeted work value per dollar of remaining actual expenditure under the simplified model. That required efficiency exceeds the observed cumulative CPI of approximately 0.889.
If the accepted cost target were instead $22,500, the corresponding calculation would be $12,000 divided by $13,500, or approximately 0.889. This equals the current CPI because the target was developed under the assumption that the existing cost efficiency continues.
If BAC minus AC is zero or negative while work remains, the original-budget TCPI no longer provides an ordinary positive feasible remaining-cost ratio. Report the condition explicitly and review the forecast and approved constraints rather than produce an unexplained division by zero or negative performance target.
Distinguish A Baseline Change From A Performance Correction
Suppose the historical society authorizes another collection for digitization. The newly agreed scope has a separate budget and planned work schedule. That is different from increasing the original baseline merely because the existing work has cost more than planned.
Record the original and revised baseline, the authorized reason and the effective timing. Preserve the historical performance record in a way that allows the relevant comparison to be understood. Our change impact assessment examples explain why an authorized change requires review of affected work, schedule and verification conditions.
Similarly, if an invoice is recorded after the status cutoff for work already performed, the team needs an appropriate accounting treatment to maintain comparable costs and accomplishment. A temporary reporting mismatch can make a particular index misleading. Correct the data in accordance with the actual reporting arrangements rather than treat the apparent improvement as established.
Check the dates and cutoffs before treating a variance as an operational problem. For example, if the team records $500 of verified accomplishment this month but the associated contractor invoice is not yet reflected in the cost record, CPI may appear temporarily favorable. An appropriate accrual or other authorized accounting treatment can reconcile costs with work already performed. Conversely, an advance payment for work scheduled for a later period should be examined under the applicable cost reporting rules. The purpose is a comparable performance measure, not a substitution of payment timing for the cost of accomplished work.
Reusable Earned Value Worksheet
| Field | Record |
|---|---|
| Status Date | Common Reporting Cutoff |
| BAC | Authorized Performance Baseline Budget |
| PV | Scheduled Budgeted Work |
| EV | Demonstrated Budgeted Work Accomplished |
| AC | Comparable Actual Cost |
| CV And SV | EV − AC; EV − PV |
| CPI And SPI | EV / AC; EV / PV |
| EAC And ETC | Forecast Under Declared Assumptions |
| VAC And TCPI | Completion Variance And Required Efficiency |
| Review | Cause, Schedule Evidence And Responsible Action |
A practical reporting package should preserve the data behind each measure and show how the performance changes over successive periods. If a project’s CPI improves from 0.8 to 0.9, determine whether the improvement reflects new efficient work, a corrected accounting mismatch or another change. The new ratio alone does not establish which explanation applies.
A useful additional check is to compare current-period and cumulative performance. Suppose a project had accumulated EV of $6,000 and AC of $8,000 at the prior checkpoint. In the next period it earns another $2,000 and incurs another $1,000. The period CPI is 2.0, but the cumulative CPI becomes $8,000 divided by $9,000, approximately 0.889. Both are mathematically correct and describe different intervals. This example illustrates why a report should identify its measurement period and avoid confusing a recent improvement with the complete project history.
Finally, keep the performance indicators connected to the actual project outcome. An apparently favorable CPI cannot compensate for a deliverable that fails its required quality condition. A favorable SPI cannot establish that the schedule-driving milestone is ready. EVM provides useful early signals when its baseline, accomplishment evidence and cost records are aligned. The subsequent investigation and decision must address the actual mechanism behind those signals.
Frequently Asked Questions
What is earned value management?
A method integrating budgeted planned work, accomplishment and actual cost.
What is PV?
The budgeted value of work scheduled by the status date.
What is EV?
The budgeted value of work accomplished under the measurement rule.
What is AC?
The actual cost incurred within the compatible reporting boundary.
How are CV and SV calculated?
EV minus AC and EV minus PV respectively.
How are CPI and SPI calculated?
EV divided by AC and EV divided by PV respectively, when defined.
Does SPI measure days of delay?
It compares budgeted accomplishment with scheduled budgeted work, not calendar days.
What is EAC?
A conditional forecast of total cost at completion.
What does TCPI measure?
The future cost efficiency required to meet a declared total cost target.
What should accompany EVM figures?
Objective accomplishment evidence, a credible baseline, accounting reconciliation and actual schedule information.