Economic Order Quantity Examples: EOQ Formula And Cost Comparisons

July 10, 2026 ·
Ordering Holding And Combined Cost Curves Across Order Quantities

Economic order quantity, usually abbreviated EOQ, is a model for choosing a replenishment lot size that balances the cost of placing orders against the cost of holding inventory. It is most useful as a transparent starting point for purchasing decisions rather than as an instruction to order exactly the calculated number regardless of supplier restrictions or uncertainty. The worked examples below build the basic model, calculate annual costs at several quantities, compare practical alternatives, and explain how the order quantity interacts with other inventory decisions.

Quick Answer

With annual demand of 3,600 units, an ordering cost of $25, and annual holding cost of $2 per unit, the basic EOQ is 300 units. Annual ordering and cycle-stock holding costs are each $300, before other relevant costs.

Table Of Contents

Understanding The Ordering And Holding Cost Trade-Off

Consider a small craft supplier that sells standard cotton cord in packs. It purchases 3,600 packs each year from an established wholesaler. Each replenishment creates approximately $25 of incremental administrative, receiving, and order-related costs. Holding one additional pack for a year costs approximately $2, including the opportunity cost of working capital, storage, and relevant inventory risks.

The supplier could purchase 3,600 packs in one annual order. That would minimize the number of replenishments but leave substantial quantities in storage for most of the year. Alternatively, it could place very small orders several times each week. This would reduce the average quantity sitting in the warehouse, but staff would spend more time preparing purchase orders, handling deliveries, and reconciling receipts.

The basic EOQ model identifies the order quantity at which the combined annual ordering and cycle-stock holding cost is minimized. The ACCA stock control technical article describes the model and its role in inventory management. The relevant input values must reflect marginal costs, not arbitrary allocations of expenses that will remain unchanged regardless of the replenishment policy.

The Basic EOQ Formula With A Worked Calculation

Let D represent annual demand in units, S the incremental cost per order, and H the annual holding cost per unit. For an order quantity Q, annual ordering cost equals D divided by Q, multiplied by S. Under the usual constant-demand, instantaneous-replenishment assumptions, cycle inventory declines evenly from Q to zero, giving average cycle stock of Q/2. Annual cycle-stock holding cost therefore equals H multiplied by Q/2.

The combined annual relevant cost is DS/Q + HQ/2. Minimizing this expression for a positive order quantity gives the square root of 2DS/H. The formula can be understood without calculus: at its unconstrained optimum, the annual ordering cost and annual cycle-stock holding cost are equal.

Using the craft supplier’s figures, 2 × 3,600 × 25 divided by 2 gives 90,000. The square root of 90,000 is 300 packs. The estimated number of orders per year is 3,600/300 = 12. Annual ordering cost is 12 × $25 = $300. Average cycle inventory is 150 packs, and the annual holding cost of that cycle inventory is 150 × $2 = $300. The two costs sum to $600 per year.

Input Or ResultAmount
Annual Demand D3,600 Packs
Incremental Order Cost S$25 Per Order
Annual Holding Cost H$2 Per Pack
Economic Order Quantity300 Packs
Orders Per Year12
Average Cycle Inventory150 Packs
Annual Ordering Cost$300
Annual Cycle-Stock Holding Cost$300
Combined Relevant Cost$600

If the supplier operates 300 selling days per year and demand is uniform, it sells 12 packs per day. A 300-pack order lasts 25 selling days. That interval is an average under the model, not a requirement that orders must occur on predetermined calendar dates. A continuously monitored system can place replenishments in response to inventory position rather than follow an inflexible monthly schedule.

Comparing Alternative Order Quantities

The calculated optimum should be interpreted alongside the cost of feasible alternatives. The formula may recommend a quantity that is inconvenient to purchase, but the cost curve near its minimum is often relatively flat. A business may be able to accommodate pack sizes, warehouse restrictions, or coordinated deliveries without sacrificing much of the modeled savings.

Order QuantityAnnual Ordering CostAnnual Holding CostCombined Cost
150$600$150$750
250$360$250$610
300$300$300$600
400$225$400$625
600$150$600$750

Ordering 150 packs doubles the order frequency compared with the EOQ, while halving average cycle stock. Ordering 600 packs does the opposite. Both alternatives cost $750 per year under the assumptions. The 250-pack alternative costs only $10 more than the optimum, an increase of about 1.67%. The 400-pack alternative increases relevant cost by $25, or approximately 4.17%.

These are differences in annual ordering and cycle-stock holding cost. They are not percentage increases in the total cost of operating the supplier’s business. If a manager presents an inventory optimization saving to senior leadership, the denominator should be explicit. The principles in cost of quality analysis are useful here: measure the costs the decision actually changes rather than imply that a reduction in a small component is a reduction in total operating expenditure.

Worked Example: Supplier Pack Sizes And Capacity Limits

Suppose the wholesaler sells cord only in cartons of 120 packs. The theoretical EOQ of 300 packs cannot be ordered exactly. The nearest feasible multiples are 240 and 360. At 240 packs, annual ordering cost is 3,600/240 × $25 = $375, while cycle-stock holding cost is 240/2 × $2 = $240. Total relevant cost is $615. At 360 packs, annual ordering cost is $250 and holding cost is $360, giving $610.

The 360-pack option is slightly better under the basic model, even though both quantities are 60 packs away from the theoretical optimum. Selecting a feasible quantity by numerical distance alone is not the same as comparing costs. Calculate the objective for the alternatives and check actual implementation restrictions.

Now suppose the warehouse has room for no more than 280 packs of this item immediately after replenishment, excluding any stock that may need to be reserved for another location. If the company maintains 40 packs of safety stock, a simplified maximum inventory approximation of Q + 40 limits the cycle order quantity to 240 packs. The 360-pack alternative is infeasible under that constraint. The best modeled unconstrained quantity and the best feasible operating policy are therefore different.

A purchasing manager should avoid describing the capacity constraint as an arbitrary adjustment to the formula. It is part of the decision problem. Document the permitted quantities, whether multiple outstanding orders can arrive together, and how peak stock is measured. Use capacity planning to evaluate the shared warehouse rather than assign each product its theoretical optimal space independently.

Worked Example: Quantity Discounts Change The Decision

Consider a different hypothetical item with annual demand of 3,600 units, order cost of $25, a standard unit price of $10, and an annual holding rate of 20% of purchase price. A supplier offers an all-units price of $9.80 when an individual order contains at least 600 units. The holding cost is $2 at the standard price and $1.96 at the discount price.

Without the discount, the EOQ is 300 units. Annual purchase expenditure is 3,600 × $10 = $36,000, and the combined ordering and cycle-stock holding cost is $600. The relevant total including purchase expenditure is $36,600.

At the discounted price, the unconstrained EOQ calculated using the lower holding cost is about 303 units, which does not qualify for the discount. Because the cost function increases beyond its unconstrained optimum, the lowest relevant cost within the discount tier occurs at its minimum feasible quantity of 600 units. At that quantity, annual purchase expenditure is $35,280, annual ordering cost is $150, and annual cycle-stock holding cost is 300 × $1.96 = $588. The resulting total is $36,018.

Cost ComponentStandard Price, Q = 300Discount Price, Q = 600
Annual Purchase Expenditure$36,000$35,280
Annual Ordering Cost$300$150
Annual Cycle Holding Cost$300$588
Annual Relevant Total$36,600$36,018

The hypothetical discount saves $582 annually after the modeled ordering and holding cost changes. Nevertheless, the larger order ties up more cash and increases peak inventory. If the item becomes obsolete before the extra units are sold, the simple calculation may overstate the value of the discount. Likewise, an incremental discount that applies only to units above a threshold requires different purchase-cost calculations from an all-units discount.

Always compare feasible candidates in every price tier, including the relevant threshold quantities. Do not merely apply the EOQ formula once at the lowest advertised unit price. The open operations management textbook on EOQ inventory models provides further context for the standard deterministic model and its assumptions.

How Changes In Demand And Costs Affect EOQ

Return to the craft supplier with D equal to 3,600, S equal to $25, and H equal to $2. Suppose annual demand doubles to 7,200 packs while ordering and holding costs remain unchanged. The new EOQ is the square root of 180,000, approximately 424.26 packs. Doubling demand does not double the optimal replenishment quantity because the quantity depends on the square root of demand.

If order preparation is automated and the incremental cost per order falls from $25 to $6.25, with demand and holding cost unchanged, the calculated EOQ falls from 300 to 150 packs. The reduction in ordering cost makes more frequent replenishment economical. However, the $6.25 figure should include real order-related receiving and coordination costs, not only the time saved by replacing a manual purchase form.

If the annual holding cost doubles from $2 to $4 per pack, with the original demand and order cost, the new EOQ is approximately 212.13 packs. A warehouse experiencing higher storage charges or increased product obsolescence may therefore choose smaller lots.

Changed InputNew Modeled EOQ
Baseline300 Packs
Demand Doubles424.26 Packs
Order Cost Falls To One Quarter150 Packs
Holding Cost Doubles212.13 Packs

This relationship makes EOQ relatively insensitive to moderate estimation errors in any individual input. But a structural error can still invalidate the decision. If the company mistakenly includes substantial fixed salaries in the incremental cost per order, its estimated order cost may be far too high. If holding costs ignore rapid obsolescence, the recommended order size may be too large. Examine assumptions through assumption mapping before treating the result as a stable policy.

How EOQ Interacts With Safety Stock And Reorder Point

EOQ addresses how much to order. The reorder point addresses when to order. Safety stock addresses the amount of protection needed against uncertainty. A standard continuous-review inventory policy can combine the three decisions but should not confuse their purposes.

Suppose the craft supplier sells 12 packs per working day, receives replenishments after five working days, and chooses a buffer of 15 packs based on a separate service analysis. The reorder point is 12 × 5 + 15 = 75 packs. The replenishment quantity is 300 packs under the baseline EOQ model. When inventory position reaches or falls below 75, the basic policy calls for placing the replenishment order, subject to documented exceptions.

If safety stock remains constant across order quantities, its annual holding cost adds a constant to the basic EOQ objective. In this example, holding 15 additional packs costs $30 per year under the simplified $2 rate. The combined ordering, cycle holding, and safety-stock holding cost is then $630 at Q = 300. Adding the constant does not move the unconstrained minimum of that particular model.

In a real stochastic system, safety stock and order quantity may interact through fill-rate targets, supplier delivery patterns, and shortage costs. A larger shipment may have a longer or more variable lead time. A different order quantity may change the frequency of replenishment cycles. Analyze those relationships rather than assume the separate textbook formulas always produce a joint optimum. See safety stock and reorder point examples for the service-level calculations that complement this article.

Building An EOQ Worksheet With Auditable Inputs

Create one spreadsheet row for each item and purchasing location. Enter demand, the period represented by that demand, the relevant cost per replenishment, annual holding cost per unit, supplier lot-size restrictions, and any stock capacity limits. Record the data source and estimation method next to the values. When demand is expressed annually, holding cost must also use an annual period.

For the standard unconstrained calculation, a spreadsheet expression can use SQRT(2*D*S/H), replacing the named values with cell references. Reject negative or zero holding cost and demand inputs rather than forcing the formula to return an apparently reasonable quantity. If demand is zero, the appropriate replenishment decision requires a separate review of whether the item should remain stocked at all.

Add candidate quantities and calculate DS/Q + HQ/2 for each. Include purchase expenditure if the purchase price changes between options. If the practical order schedule has integer periods, seasonal demand, or coordinated deliveries, model that schedule directly. Annual order counts such as 3,600/250 = 14.4 are long-run cost estimates, not literal instructions to place a fraction of an order in a specific year.

Validating The Inventory Decision In Practice

Before adopting a new order size, compare historical and proposed policies against actual demand, replenishment events, inventory peaks, and shortage outcomes. The simple EOQ model assumes stable demand, known costs, consistent replenishment, and no shortage costs within the objective. It is not designed to resolve every situation involving uncertain demand, finite production rates, perishable inventory, or shared transportation constraints.

A supplier with demand that is strongly concentrated in a few months may benefit from a time-phased replenishment plan rather than an annual average lot size. A supplier making the item internally at a finite rate may require a production quantity model rather than assume instantaneous receipts. A company that coordinates orders for many items on one truck should evaluate joint ordering costs, not optimize each item as though every order were independent.

Use the approach described in post-implementation reviews to compare realized costs and service after a trial. Check whether the expected reduction in receiving work or average inventory actually occurred. Record stockout costs, emergency orders, inventory discrepancies, and working capital consequences separately. A reliable EOQ decision is supported by a reproducible calculation, explicit feasibility constraints, and evidence that the operating policy improves the outcomes the business values.

Frequently Asked Questions

What does economic order quantity calculate?

EOQ calculates the unconstrained replenishment lot size that minimizes annual ordering and cycle-stock holding costs under the basic model.

What is the standard EOQ formula?

EOQ equals the square root of 2DS/H, where D is annual demand, S is cost per order, and H is annual holding cost per unit.

Why do ordering and holding costs balance at EOQ?

At the unconstrained optimum, their marginal trade-off produces equal annual ordering and cycle-stock holding cost.

Should I round EOQ to the nearest whole unit?

Compare feasible quantities around the result and include supplier pack sizes, minimum orders, storage limits, and relevant costs.

Does EOQ include purchase price?

Constant purchase expenditure does not affect the basic optimum. Quantity discounts require comparison of purchase, ordering, and holding costs.

What happens if demand doubles?

With unchanged order and holding costs, EOQ increases by a factor of the square root of two.

Is EOQ the same as reorder point?

EOQ determines how much to order; a reorder point determines when replenishment is triggered.

Does safety stock change EOQ?

A fixed safety stock adds a constant holding cost in the basic model. More complex policies may link buffer and order size.

Can EOQ be used for seasonal items?

A stable-demand calculation can be a benchmark, but seasonal demand may require time-phased replenishment modeling.

How do I validate an EOQ policy?

Compare realized ordering costs, inventory levels, service outcomes, and constraints against the baseline after implementation.