Three Branching Scenarios With Distinct Outcome Profiles

Risk and scenario analysis helps people prepare for uncertainty without pretending to know exactly what will happen. A risk describes an uncertain event or condition and its potential effect on an objective. A scenario is a coherent account of conditions that might arise. Comparing scenarios can reveal where a plan is vulnerable, which preparations are useful across several futures and when a different response is needed. The examples in this guide use fictional data and general operational situations, not regulated safety, medical, investment or legal recommendations.

Quick Answer

Identify the objective, describe uncertain causes and their consequences, assess likelihood and impact with consistent scales, compare credible scenarios, select proportionate responses, assign owners and define review triggers. Keep assumptions visible and prepare alternatives before an uncertain event forces a rushed decision.

Table Of Contents

Risk, Issue, Assumption And Scenario

A risk is uncertain. An issue is already occurring and requires management now. An assumption is an unverified condition used for planning. A scenario combines possible future conditions to explore how an option could perform. If a required venue has already been canceled, the cancellation is an issue, while the possibility that the replacement will also become unavailable remains a risk.

TermIllustration
ObjectiveRun a workshop with reliable access for registered participants
AssumptionThe agreed room will be available
RiskThe room becomes unavailable before the event
IssueThe room has been canceled
ScenarioDemand rises while available rooms become limited

The ACT Treasury risk analysis guidance discusses identifying, assessing and documenting uncertainties. Use a scale suitable for your own objective. A small volunteer project does not require the same analysis as a regulated infrastructure project. For consequential specialist risks, use the relevant qualified expertise and mandatory standards.

The 360 ES Risk Analysis Framework

Start by identifying the decision or objective at risk. Write a risk statement as cause, uncertain event and consequence. For example, because several volunteers are available only on weekends, a weekday orientation may have insufficient attendance, delaying readiness. This statement identifies a mechanism and a possible effect without implying that the event is certain.

DimensionPractical Question
ContextWhat objective or deliverable is exposed?
CauseWhat condition could lead to the uncertain event?
LikelihoodWhat evidence supports its plausibility?
ImpactWhich outcome, group or resource might be affected?
ControlsWhat already reduces exposure?
AlternativesWhat preparation or response is feasible?
TriggerWhen should action or escalation occur?
ReviewWho owns the risk and when is it reassessed?

Do not treat a list of risk titles as a completed assessment. The owner should understand the relevant assumptions, current controls and action required. Use the problem solving guide to distinguish a plausible cause from a confirmed cause, and revisit the risk as the evidence changes.

Example: A Practical Likelihood And Impact Matrix

A workshop coordinator creates a three-level ordinal scale. Likelihood levels represent low, medium and high plausibility within the planning period. Impact levels represent minor inconvenience, significant disruption and inability to meet an essential objective. The scale is an example of an internal ranking aid and is not a statistical probability model.

Likelihood / ImpactMinor 1Significant 2Major 3
Low 1123
Medium 2246
High 3369

Multiplying the numerical labels provides a simple prioritization convention. A score of six is not proven to be twice as risky as a score of three, since the categories are ordinal. Two risks with equal scores can have very different consequences. A low-likelihood risk that prevents an essential objective may require a prepared response even when its score is below that of a frequent inconvenience.

The owner can use the score to structure discussion and decide which items require further evidence. Mandatory requirements are handled separately. Document why a likelihood rating was chosen, distinguish unknown from low, and assess remaining exposure after controls are implemented rather than assuming a planned control already works.

Example: Building A Risk Register

RiskL × IPrepared ResponseTriggerOwner
Orientation attendance too low2 × 3 = 6Arrange backup sessionFewer than required confirmationsTraining Lead
Materials arrive late2 × 2 = 4Identify available substitutesDelivery unconfirmed by agreed dayMaterials Lead
Requests exceed capacity3 × 2 = 6Set clear admission and overflow rulesBookings reach capacityCoordinator
Room becomes unavailable1 × 3 = 3Verify alternative venueNotice of cancellationEvent Owner

This hypothetical register records actions before the events occur. Each trigger is observable or must be translated into an exact threshold appropriate to the plan. Before assigning a backup venue, verify that it meets the essential requirements, including accessibility and availability. A fallback that cannot be activated in time is not a usable contingency.

Add a status, review date, existing controls and residual assessment when operating the register. Do not erase a risk simply because an owner has been assigned. The owner needs the authority and resources to carry out the response, and the responsible decision maker must determine whether the remaining exposure is acceptable.

Example: Scenario Planning With Two Uncertainties

The UK Government Futures Toolkit describes using uncertain conditions to explore several possible futures. A fictional community workshop faces uncertainty about registration demand and facilitator availability. The two uncertainties are relevant because they influence what the event can deliver, but they are not the only possible influences.

ScenarioDemandFacilitatorsImplication
ALowerFull TeamUse smaller groups; avoid unnecessary setup
BHigherFull TeamUse planned capacity and overflow list
CLowerReduced TeamSimplify program while preserving access
DHigherReduced TeamLimit attendance to verified capacity; arrange later session

The four scenarios are not assigned probabilities because the team lacks credible estimates. Compare the same plan in each scenario and identify which preparations are useful across them. A clear registration cutoff, an accurate count of available facilitators and prewritten participant messages help in several futures. Additional session capacity is useful only if suitable people and space are available.

Choose indicators that reveal emerging conditions: confirmed registrations, facilitator confirmations and access to rooms. Set decision deadlines for changes to the event format. Scenarios should remain plausible and internally coherent, not become arbitrary labels for optimistic and pessimistic guesses.

Example: Estimating An Expected Disruption

A coordinator compares two ways to prepare a shared activity. Under an illustrative model, an essential component has a 20 percent chance of being unavailable, causing six hours of disruption if there is no backup. With a verified backup, the assumed disruption would be one hour. Expected disruption is probability multiplied by consequence: 0.20 × 6 = 1.2 hours without backup and 0.20 × 1 = 0.2 hours with backup.

The backup requires 45 minutes of preparation. If time is the only measure and all assumptions hold, the combined expected preparation and disruption is 0.75 + 0.20 = 0.95 hours. The comparison favors the backup by 0.25 hours on this simplified expected-value measure. This does not guarantee a time saving in a particular event. If the component is available, the team may spend preparation time without using the backup.

The break-even probability can be derived from 0.75 = p × (6 − 1), giving p = 0.15 or 15 percent. A lower assumed probability changes the time-only comparison. A serious disruption may still justify a backup for reasons not represented by expected hours. Check probability estimates, timing, alternative impacts and whether the backup introduces new risks before using the model.

Example: Comparing Robust Alternatives

Consider three possible event layouts under different levels of attendance and staff availability. The following numbers represent hypothetical suitability scores on an agreed 0 to 100 scale. They are neither financial values nor actual measured outcomes.

OptionLow DemandHigh DemandReduced StaffingWorst Score
Fixed Large Layout55904040
Flexible Layout75806565
Fixed Small Layout90457045

The flexible layout has the best worst-case score of 65 under these scenarios. A decision maker who prioritizes robustness might prefer it, provided it meets every mandatory requirement. The fixed large layout performs best in high demand but is vulnerable when staffing falls. The fixed small layout is attractive for low demand and reduced staffing but may not accommodate high demand.

A different set of scenarios or scoring assumptions could reverse the recommendation. The matrix is useful because it identifies vulnerabilities rather than predicting the future. Use the decision making guide to compare trade-offs and record how uncertainty influences the choice.

Contingencies, Triggers And Ownership

A contingency plan states what action will occur if an agreed condition is met. For a small event, the trigger may be the number of confirmed facilitators two days before opening. The response might be reducing the number of simultaneous activities, communicating a revised schedule and offering an additional session later. Specify who can authorize the change and what must be ready.

A risk response may avoid an exposed activity, reduce the chance or consequence of an event, share some responsibility by appropriate arrangements, or accept a residual risk after review. Transferring a task does not automatically transfer every consequence or obligation. Make sure the relevant party can perform the response.

Review triggers should allow enough time to act. A signal received only after the activity becomes impossible may be too late to activate a fallback. The planning and implementation guide covers dependency schedules and readiness gates. The systems thinking guide explains how responses to one risk can create consequences elsewhere.

Risk And Scenario Analysis Worksheet

FieldWhat To Capture
Objective And BoundaryWhat could be affected and over what period
Risk StatementCause, uncertain event and consequence
Evidence And AssumptionsObserved data and uncertain judgments
Existing ControlsWhat is already operating
AssessmentLikelihood, impact and explanation
Scenario TestsHow alternatives perform under different conditions
Response And OwnerAction, accountable person and resources
TriggerObservable condition and decision deadline
Residual RiskRemaining exposure after verified controls
ReviewStatus, next date and evidence of effectiveness

Consider which measurements matter for the people affected. A solution that reduces operational disruption by excluding difficult cases may worsen access. Record balancing measures and limitations. If the evidence supports only a qualitative conclusion, avoid presenting a numerical estimate as if it were a precise forecast.

Use the worksheet as a living record. New information can change the probability of a risk, reveal that an assumption is invalid, or convert a risk into an issue. Review the most important exposures at appropriate intervals and close them only when the reason is documented.

Frequently Asked Questions

What is risk analysis?

It evaluates uncertain events and their possible effects on objectives, taking account of evidence, existing controls and feasible responses.

What is a scenario?

A scenario is a plausible combination of future conditions used to examine how an action or plan might perform.

Is a scenario a prediction?

Scenarios explore possibilities. They should not be presented as guaranteed forecasts.

What is a risk register?

It records risks, assessments, controls, owners, responses and review information.

How do you score a risk?

Choose clearly defined likelihood and impact scales. A product of category labels is a prioritization convention, not necessarily a quantitative measure.

What is residual risk?

It is the risk remaining after the relevant controls and responses are in place.

When should a contingency be activated?

When a defined trigger is reached and the authorized owner confirms the response is appropriate.

What is expected disruption?

It is a probability-weighted average of disruption across possible outcomes, under the assumptions of the model.

How can scenarios help choose a solution?

They reveal which options perform acceptably across plausible futures and which require additional safeguards.

How often should risks be reviewed?

Review according to the consequence, changing conditions and decision deadlines. Reassess when relevant evidence or assumptions change.