Resource leveling and resource smoothing help turn a schedule that is mathematically plausible into a plan that can actually be performed with available resources. A network of tasks may show two activities occurring simultaneously because neither depends on the other. That does not establish that the same specialist can perform both at once. The following original fictional examples distinguish a resource conflict from a logical dependency, show when available float can resolve a workload peak and explain when completion must change unless a suitable alternative is available.
Quick Answer
Build the dependency-based schedule, calculate time-phased resource demand and resolve conflicts. Smoothing adjusts work within permitted timing flexibility; leveling prioritizes resource limits and may change the completion date.
Table Of Contents
- Distinguish Resource Leveling From Resource Smoothing
- Worked Example: Prepare A Museum Postcard Collection
- Calculate The Resource-Constrained Schedule
- Worked Example: Smooth Work Within Available Float
- Calculate A Resource Profile In Hours
- Distinguish Divisible Work From Indivisible Tasks
- Worked Example: Compare Two Project Commitments
- Compare Leveling With Adding Suitable Capacity
- Reusable Resource Leveling Worksheet
- Frequently Asked Questions
Distinguish Resource Leveling From Resource Smoothing
The Association for Project Management explanation of resource smoothing and levelling distinguishes a time-constrained approach from a resource-constrained approach. Resource smoothing generally seeks a more suitable resource profile within the available schedule flexibility. Resource leveling gives greater priority to the resource limitations and can alter the project completion date or schedule-driving path.
Both methods begin with a credible definition of the required activities. A schedule cannot be leveled meaningfully if the task durations represent inconsistent scopes or if required work is missing. Establish the predecessors, durations, actual resource requirements and relevant calendars before considering timing adjustments.
Our Gantt chart examples show how a project schedule can represent activities and timing relationships. Resource analysis adds another dimension: how much of each suitable resource the schedule requires during every relevant time interval.
A resource can be a person, an approved review role, an appropriately available preparation station or another limited capability. Two resources that appear identical in an organizational chart may not be interchangeable for a specific activity. Record the relevant capability and availability rather than treating every person-hour as equivalent.
Worked Example: Prepare A Museum Postcard Collection
A fictional small museum shop is preparing an approved set of historical postcard displays. Its project contains four activities. Establishing the approved content list comes first. Two separate preparation activities can then begin, followed by a coordinated final review. The simplified durations are in whole operating days.
| Activity | Duration | Predecessor | Resource |
|---|---|---|---|
| A: Confirm Content List | 2 Days | None | Coordinator |
| B: Prepare Caption Cards | 3 Days | A | Editorial Specialist |
| C: Prepare Display Labels | 2 Days | A | Editorial Specialist |
| D: Complete Final Review | 1 Day | B And C | Reviewer |
A dependency-only schedule begins at day zero. Activity A occupies days one and two. B and C can logically begin on day three. B finishes at the end of day five and C at the end of day four. D occupies day six, so the dependency-based finish is day six.
The problem is that B and C require the same editorial specialist at full capacity for their entire durations. The schedule therefore asks for two units of that resource during days three and four, when only one is available.
The initial critical path through A, B and D lasts six days. The branch through A, C and D lasts five days. C has one day of total float under the dependency-only model. That float is insufficient to move the entire two-day task beyond B without changing the project finish.
Our dependency mapping examples explain how a shared resource creates a practical relationship between otherwise independent activities. The editor’s limited availability does not change the underlying content dependency, but it constrains the feasible order of work.
Calculate The Resource-Constrained Schedule
One feasible arrangement performs B on days three through five, C on days six and seven, and D on day eight. The alternative order performs C on days three and four, B on days five through seven, and D on day eight. Both require five consecutive editorial resource-days after A.
| Activity | Dependency-Only Schedule | Resource-Constrained Schedule |
|---|---|---|
| A | Days 1–2 | Days 1–2 |
| B | Days 3–5 | Days 3–5 |
| C | Days 3–4 | Days 6–7 |
| D | Day 6 | Day 8 |
| Completion | Day 6 | Day 8 |
The two-day difference reflects a resource limitation, not a change in the amount of work. The project still requires the same defined preparation and final review. An accepted six-day commitment would need a different feasible resource or work arrangement.
The Project Management Institute scheduling and resource leveling discussion describes how a resource limit and a project finish constraint can lead to different scheduling objectives. Running a resource-constrained calculation and a time-constrained calculation can help make the trade-off visible.
In the museum example, simply retaining the original six-day finish in a plan does not resolve the conflict. Nor does changing the assigned resource label to another person establish that suitable editorial capacity exists. Verify the actual capabilities and availability required by the schedule.
Worked Example: Smooth Work Within Available Float
Consider a second fictional project preparing a small exhibition booklet. Activity A requires two days of general preparation. Activity B follows A and requires four days of editorial work. Activity C requires two days of editorial work but can begin at project start. Final verification D requires one day after both B and C finish.
In the initial arrangement, suppose C is scheduled on days three and four by preference, while B occupies days three through six. The same editorial specialist is assigned to both, causing a conflict. Unlike the first project, however, C has no predecessor and can legitimately occur on days one and two while A is performed by a separate suitable role.
| Activity | Initial Assignment | Smoothed Assignment |
|---|---|---|
| A | Days 1–2 | Days 1–2 |
| B | Days 3–6 | Days 3–6 |
| C | Days 3–4 | Days 1–2 |
| D | Day 7 | Day 7 |
Moving C to the beginning removes the editorial conflict without changing the day-seven completion. The total editorial work remains six resource-days. This is a useful example of adjusting work within schedule flexibility rather than increasing the overall project duration.
The feasibility depends on the stated conditions. If C actually requires the content approval produced by A, then moving C to days one and two would violate a predecessor relationship. Do not treat an incomplete network as evidence that the task can be shifted. The team should verify the real prerequisite before accepting the adjusted schedule.
Our work breakdown structure examples explain how a defined scope is decomposed into meaningful work components. A task definition that is too broad may conceal activities with different prerequisites. Decomposing it appropriately can reveal legitimate flexibility without inventing an overlap that cannot occur.
Calculate A Resource Profile In Hours
A fictional textile sample library has a shared indexing role available for six suitable hours each operating day. Three distinct assignments require a total of 24 hours over five days. The initial workload profile is four, eight, seven, three and two hours.
| Day | Available Hours | Initial Load | Revised Load |
|---|---|---|---|
| Monday | 6 | 4 | 5 |
| Tuesday | 6 | 8 | 6 |
| Wednesday | 6 | 7 | 6 |
| Thursday | 6 | 3 | 4 |
| Friday | 6 | 2 | 3 |
| Total | 30 | 24 | 24 |
The initial weekly total is below the 30-hour availability, but Tuesday is overloaded by two hours and Wednesday by one. The combined positive overload is three hours. The revised profile removes these peaks by moving three compatible hours into other eligible days while retaining the total workload.
The revised profile is possible only if the affected work can genuinely move. If Tuesday’s eight hours concern records that must all be accepted before the end of Tuesday and none can be prepared beforehand, shifting them to Wednesday or Friday would miss the requirement. The aggregate profile is not enough to establish feasibility.
Our capacity planning examples explain how a favorable weekly total can conceal a shortage in a particular time window. Resource leveling operates on that time-phased detail and must preserve the applicable commitments.
A useful measure is maximum demand relative to available capacity. In the initial profile the peak load is eight hours against six, or approximately 133.3%. In the revised profile the peak is six, or 100%. The mean load remains 4.8 hours per day. The improvement lies in the distribution rather than a reduction in total required work.
Distinguish Divisible Work From Indivisible Tasks
The previous profile assumes that some work can be moved in compatible hourly portions. Not every activity can be interrupted or divided in that way. A particular review might require three consecutive hours with the same approved records available. Three free one-hour intervals on different days would not satisfy that arrangement.
Suppose the library has four separate free intervals of 90 minutes across the week. Together they provide six hours of nominal availability. An activity requiring a continuous four-hour session cannot fit any of them. Counting total availability without considering the required continuity would create an infeasible assignment.
Where splitting is legitimate, represent the effect of interruption. Resuming work may require preparation, context reconstruction or another review of the current information. Our setup reduction examples distinguish interruption time and supporting preparation effort. A leveling model that divides tasks into very small parts should account for any additional work that the division creates.
A practical schedule should also preserve reasonable operating conditions for the people doing the work. Do not treat necessary rest, agreed working boundaries or other obligations as automatically available capacity simply because a software model can place an activity into those intervals.
Worked Example: Compare Two Project Commitments
Consider a fictional specialist who prepares approved artwork references for two independent stationery projects. Project X requires three specialist-days and has an accepted checkpoint at the end of day three. Project Y requires two specialist-days and has an accepted checkpoint at the end of day five. Both work components are ready at the start of day one and can be performed without interruption.
If the specialist completes Y on days one and two, X occupies days three through five and misses its day-three checkpoint. If X is performed on days one through three and Y on days four and five, both checkpoints are met under the simplified assumptions.
The workload totals are the same, and both sequences finish all specialist work on day five. The sequence affects whether the earlier commitment can be met. A resource-leveling rule based only on the shortest task first would make a poor choice in this example.
Our weighted shortest job first examples show how time-dependent consequences can influence sequencing. A leveling decision should consider actual due dates, dependencies and eligible commitments rather than rely exclusively on a single generic priority rule.
If Project X is not actually ready until day two because its approved reference is unavailable, the feasible options change. Completing X by day three would require a two-day duration rather than three. That may need a verified acceleration option or a different accepted commitment. Updating the schedule with the current readiness information is essential.
Compare Leveling With Adding Suitable Capacity
Return to the museum postcard project. The resource-constrained plan finishes on day eight. If an independent suitable editorial resource can perform C during days three and four, the original six-day dependency-based schedule may become feasible.
The organization should compare the additional resource cost, coordination effort and actual accepted outcome with the consequences of the longer schedule. Merely assigning a second resource does not guarantee equivalent results. The resource may need orientation, access to the approved content list and appropriate verification arrangements.
Our project crashing examples examine the trade-off between additional direct cost and shorter completion. Adding a resource to address a scheduling conflict may be a valid acceleration mechanism, but the real duration, work and cost consequences need to be represented.
Suppose obtaining the second editor requires two additional hours of coordination from the first editor before C can begin. That coordination may affect B’s schedule if the first editor was already fully occupied. Recalculate the actual network rather than assume that the original six-day arrangement is restored without any additional work.
Compare the total resource profile with each individual’s actual calendar. If two suitable editors are available for six hours each on Tuesday, an assignment requiring twelve editor-hours fits the aggregate only if the work can be divided between them in a compatible way. A task requiring eight hours of continuous work from one editor still cannot fit either person’s six-hour window. Similarly, a simultaneous meeting consumes time from each participant, not merely one generic editorial resource. Preserve both the aggregate resource category and the actual person or station constraints where they affect the decision. This prevents a favorable histogram from hiding an infeasible assignment.
Reusable Resource Leveling Worksheet
| Field | Record |
|---|---|
| Activities | Defined Work, Durations And Predecessors |
| Resource | Required Capability And Quantity |
| Calendar | Actual Available Time And Existing Commitments |
| Initial Schedule | Start And Finish Boundaries |
| Profile | Resource Demand By Relevant Interval |
| Conflicts | Overload, Timing And Shared Conditions |
| Candidate Change | Within-Float Shift, Resequence Or Suitable Capacity |
| Revised Schedule | Completion, Workload And Remaining Gaps |
| Verification | Actual Availability, Accepted Output And Timing |
Check the revised plan against the complete network and the actual resource calendars. An automated leveling feature may produce a mathematically valid schedule under its settings while splitting tasks in undesirable ways or using priorities that do not reflect the organization’s commitments. Review the output with the people responsible for the work and adjust the model where its assumptions are unsuitable.
Resource leveling is also a continuing planning activity. As actual progress becomes available, the remaining workload and resource requirements may change. Preserve the baseline and record the reason for a revised sequence so performance reporting remains interpretable. Our earned value management examples distinguish an approved baseline from subsequent performance and completion forecasts.
A useful final exercise is to verify the resource profile from the revised schedule rather than assume every movement reduced overload. Moving one task away from a busy Tuesday may create a new conflict on Thursday. Recalculate every affected resource interval, including shared reviewers who support multiple activities. A resource-feasible plan is one in which the work, timing, capabilities and accepted results can coexist under the actual constraints.
Frequently Asked Questions
What is resource leveling?
Adjusting a schedule to accommodate actual resource limitations, potentially changing completion.
What is resource smoothing?
Adjusting resource demand within permitted schedule flexibility while preserving the intended finish.
What causes resource overallocation?
Scheduled work requires more of a resource during an interval than is suitably available.
Can a dependency-only schedule be infeasible?
Yes, independent activities may compete for the same limited resource.
What is float?
Schedule flexibility under the specified network and completion constraints.
Can tasks always be split?
Only where the actual work and requirements permit division and interruption.
How is overload measured?
Compare required and available compatible resource quantities for the same time interval.
Does leveling reduce total work?
Not necessarily; it often changes timing rather than effort.
Can leveling affect the critical path?
Resource-driven adjustments can change the schedule-driving sequence.
How should a revised schedule be verified?
Check dependencies, actual resource availability, commitments and the accepted completion condition.